Development of the Little Aden Oil Refinery
In March 1951 the Iranian government
nationalised the Anglo-Iranian Oil Company’s
(AIOC’s) refinery at Abadan on the Persian
Gulf. The AIOC as a matter of urgency had to
identify other possible locations for a new
refinery. Aden was soon short-listed,
principally because of its geographic
location between the Gulf and Suez but also
because of the market potential of the ships
that called at Aden.
The man at the Colonial Office dealing with
a potential application to build a refinery
at Aden was none other than
Sir Bernard
Reilly, now almost 70 and working as
a consultant. He thought the Governor,
Sir Tom
Hickinbotham, would welcome the
project as long as a suitable site with
sufficient space could be found. But
Hickinbotham had very mixed feelings about
the idea, principally because of the
inflationary pressures it would have on the
Aden economy.
AIOC sent a party out to examine the
possibilities and they reported back
sufficiently favourably for detailed surveys
and planning to be undertaken. The Chairman
of AOIC was keen to avoid the creation of a
refinery community socially and materially
detached from the rest of the Colony – and
in this he would be ultimately totally
unsuccessful. It was envisaged that when
operational the refinery would employ over
3,000 men, including around 400 Europeans.
During construction the numbers would be
much greater, some 2,000 Europeans or
Americans and a labour force of around
7,500. The refinery and associated
infrastructure would take two years to
build.
Little Aden was not the only location
considered. Another possibility was to build
the refinery and a new port on the northern
side of the Inner Harbour in the area of
Hiswa, referred to
as ‘within the arms of the Rubble Mound’.
This would have allowed the desired
integration with the existing community but
the biggest drawback was that it would take
three years to dredge a channel to the new
port – far too long for AIOC which needed to
get a new refinery operating as soon as
possible. The half-and-half option of a port
at Little Aden and a refinery in the area of
Hiswa was considered uneconomic due the cost
of laying a steel pipeline between the two
areas. Hence Little Aden was selected, with
the new port to be built in the area of
Pinnacle Rock, with initially four oil
berths, one cargo jetty, a turning basin and
a dredged channel sufficiently large to take
the largest tankers then operating (32,000
tons). The throughput capacity of the
refinery would be five million tons a year
(which it is believed equates to only
170,000 barrels a day). The total area to be
used was some 270 acres.
|

Dorsetshire |
A project programme was issued in
February 1952 and a memorandum of
understanding published in June and
on 15 July a pilot construction team
arrived in Aden. The target date for
completion and beginning operations
was September 1954, (in which year
Anglo-Iranian changed its name to
British Petroleum). |
At the start Little Aden was totally lacking
in infrastructure and the problem of housing
the European workers was largely solved by
using a former troopship, the 9,500 ton
Dorsetshire, for accommodation.
The refinery was opened in 1954 as forecast,
with a capacity of 170,000 barrels a day -
which apparently was never achieved. It was
working at well below capacity when it was
nationalised in 1977 following the British
withdrawal from Aden. The installations were
badly damaged in the civil war of 1994 which
reduced capacity even further to 60,000 to
70,000 barrels a day. In 2005 capacity was
still around 70,000 barrels – sufficient for
local needs but not much more.